PUTRA HEIGHT CONDOMINIUM – High-Rise Transformer Replacement (11KV)

Empowering High-Rises with Safe and Efficient Energy

Ohmmega successfully replaced and upgraded the main 11KV transformer for Putra Heights Condominium, ensuring uninterrupted power supply for all residents. The project involved precise planning, safe removal of the existing transformer, and installation of a modern high-capacity unit to support the building’s electrical demands.

Transforming energy, transforming comfort.

Approach

The project focused on upgrading the high-rise electrical infrastructure to maintain safety, reliability, and efficiency for residential power consumption.

Project Maintenance

Regular inspections and maintenance of the new transformer, switchgear, and distribution system to ensure ongoing reliability and safety.

More Detail

This project minimized downtime during replacement and ensured that residents continued to receive uninterrupted power. All works complied with high-rise electrical safety standards and included testing, commissioning, and certification of the upgraded system.

The existing transformer had reached its operational limits and needed upgrading to meet growing electrical demands safely.

Power was managed carefully to minimize downtime, and temporary arrangements were made to ensure essential supply.

Yes, periodic inspections, testing, and preventive maintenance are included.

The timeline was planned to minimize inconvenience, typically executed over a few days with safety measures in place.